Hamirpur, October 23: Power supply to parts of Tauni Devi, Galod and Mattansidh areas will remain partially disrupted for an hour on October 27 due to the installation of a new transformer at Anu Power Substation.
Suresh Kumar, Assistant Engineer at Anu Power Substation, said the disruption may affect areas served by the 33 kV feeders of Tauni Devi, Galod and Mattansidh between 7 am and 8 am.
He advised residents of the affected areas to make necessary arrangements in view of the scheduled work.